The Famous Bay
Bridge Crack
Tony Alfrey (tonyalfrey at earthlink
dot net)
Latest update: 3:00 AM PST, Wednesday, Jan. 13, 2010
Repair
All Finished! You heard it first here on Dec. 22,
2009.
The Bay Bridge Tutorial is nearing
completion, where you can
actually calculate the stress on the broken bridge parts! Try it!
Special thanks to:
Eric Case for his Twitter post,
Jeff Grafton for the heads-up on the photo archive, Laughing
Squid, various
readers with
their great comments, WPI, the crew that designed
www.baybridgeinfo.org, Dreamhost (they host
my website and they are pretty decent), Caltrans for their initial
obscure reports that provided the
motivation for this page, and my anonymous sources.

Contents
Motivation
In the early evening of October 27, 2009, a repair that had been made
on the San Francisco-Oakland Bay Bridge failed spectacularly, and was
captured nearly in real-time and posted on Twitter. The
subsequent
unsatisfying explanation for the failure by Caltrans, the agency
responsible for
the repair, prompted me to ask "can I figure this out?". Our
guesses were pretty close to the official
pronouncement
issued days later. Now, months after this page was
originally posted, the story
could be compressed and simplified. But that would miss the
point, which is that it was possible to solve a mystery by using photos
and
pieces of data available on-line. Our writing style can seem a
little disjointed because we've written the page in many, many pieces
over an
extended period of time, and have left some of the parts as originally
written without revision to try to display the original style by which
the "blog" evolved.
As of the latest update in January, 2010, this is all ancient
history! All of these parts are gone, and replaced by Repair 3.0.
But it still deserves some consideration:
Those who cannot remember the past
are condemned to repeat it. - George Santayana.
Introduction
This is not one of my usual Noon Science experiments, but there's some
cool stuff to learn anyway. We'll work on this as the "week"
(first
posted
Oct. 28) progresses and as more info and pictures become available.
OK, so if you're not from the San Francisco Bay area, you might not
know that our famous Bay Bridge (a.k.a. San Francisco Oakland Bay
Bridge) is undergoing a big earthquake
retrofit. Here's a CAD model of the new eastern span (the part
that goes from Yerba Buena Island in the middle of the bay over to
Oakland), viewed from Yerba Buena Island, that will replace the old
eastern span deemed unsafe after the Loma Prieta earthquake.
Get all the details (and this picture) here.
Below is a photo of the current bridge taken from roughly the same
location as above. The plan for Labor Day of 2009 was to install
a section (the white thing in the foreground) into the
temporary S-section of the bridge so that traffic could be rerouted (to
the right) around the
portion (to the left) which will
be connected to the new Bay Bridge (in the background); a rather
remarkable achievement in my opinion. By the way,
these dudes should get some
credit for this; check out their cool animation.
But while all of this was going on, engineers performed an inspection
of the entire eastern span of the bridge, and found a little problem,
and everyone forgot all about this cool detour thing. Here is a
picture of the Bay Bridge before modifications had
begun.
The circle shows where our little problem, a crack, was found:
(Picture from here
and here. Also, see
other fine aerial photography in LA, my hometown, here)
What Crack?
Here is a close-up view of the crack, that rusty-looking opening, in a
piece called an Eyebar. The crack is big enough to slip your hand
inside.
At 7:07 in
this
video, you can see what Eyebars look like (albeit for the
west span), all stacked up and
being
prepared for installation.
(Picture here
and more broken bridge info from the San Jose Mercury News)
There was a substantial rush to open
the bridge after Labor Day weekend, so some "repairs" were made, but
not much detail (at first) was available describing what was actually
done. On
the evening of Oct. 27, in the middle of rush hour, the repair
broke. Can we figure out what happened?
The Initial Repair (Repair 1.0)
Here is a picture of the section of the bridge where the repair was
made.

|
|
As you look at this picture, you'll see two
different kinds of
stick-like structures that make up the bridge. The first thing is
called a Lattice Girder. It is the part that looks like a long,
rectangular open-sided box, with a criss-cross-hatching of
straps. These parts are generally under compression, that is,
they are being pushed from each end with a force that tries to shorten
the girder *. The second
important part is
a so-called
Eyebar. They are simple, long, wide, flat straps with big round
knobs on each end. They are on the right side of this picture and
they go diagonally from the road bed up to the top of the bridge.
They are arranged in pairs. There are Eyebars that go in the
center and there are Eyebars that connect to the road surface at the
bottom and to the Lattice Girders at the top. These Eyebars are
in tension, that is, they are
being pulled at each end with a force
that tries to lengthen the Eyebar. So the crack is in the very
top end of the central Eyebar. The crack is big and open, because
the tension on the Eyebar tries to pull the crack further apart.
And of the literally hundreds of components on the bridge, this eyebar
is part of a significant load-bearing assembly.
|
OK, so what to do? Well, I first
speculated that the solution
derived from tooling originally used to
construct the bridge. But it turns out that when the bridge was
first constructed, each girder or eyebar was hung onto the end of the
finished portion of the bridge as each section "walked out" (see this) from the twin supports, and
this
won't work as a repair technique once the bridge is under load.
The load (in this case, a tension
) must be removed from the broken piece before repairs can be
made. The solution was designed by engineers at C. C. Myers, and the components were
fabricated almost
overnight by Stinger Welding
in
Arizona, without much time for a thorough analysis,
especially with respect to resistance to vibration. This
is how it works.

(Picture from Sacramento
Bee here,
rumored
to have actually originated here)
|
|
First,
we need a
Saddle. This is a half-cylinder-like thing that
sits on the cylindrical Pin connecting the Eyebars. Then, on top
of the Saddle,
they put a large T-shaped slab of steel, that Caltrans calls a
Crossbar, that holds
the Tie Rods. These Tie Rods (four all together) are just very
long bolts with Nuts
on the end that are adjusted to tension (tighten by pulling) the Tie
Rods (see correction
at
bottom of page) . They install
this assembly at each end of the Eyebar and tighten up the Nuts.
Done.
The four Tie Rods (they look like
about an inch and a half or two inches in diameter) do the job of an
Eyebar
(12 3/8" wide and 1 13/16" thick to be exact)? Were
they made of the conventional A36 steel used in most bridge
construction, and in the Bay Bridge,
the Tie Rods would have been way too small. Months
after the original failure, we find out that the Tie
Rods are Williams
Rods,
fabricated from a high-tensile-strength steel.
In principle, the steel used in these Tie Rods should have
tolerated the tensile (stretching)
load. See our Tie
Rod stress calculations here.
|
Here is a view of the
installation taking place. The Saddle is in
place, along with the Crossbar on top.
The Tie Rods have not been installed yet.
Here is a much better picture
added on
Oct. 30, showing the Saddle
being installed, along with the Crossbar on the top that holds the
Tie Rods.

|
|
A
lot can be
learned from this picture. This Saddle (hanging from
the crane on the left) fits over the cylindrical Pin that connects
the two Eyebars. The Tie Rods must pull on each side of
the Saddle to keep the Saddle in place, but the Saddle must be able to
slide in between the pair of Eyebars. The big T-shaped Crossbar
(on
top of the Saddle) holds one pair of Tie Rods, but there must be another Crossbar on the other
side of the Saddle which has not been installed yet. It must be
installed after the Saddle is slid between the Eyebars. Then the
Tie Rods are installed. Look to the right side of the
picture where you can see the diagonal Eyebars where the Saddle will be
installed. You will see the big crack in the Eyebar just below
the Pin.
If you study the picture carefully, and try to visualize assembling the
pieces, you will conclude that one needs a little change in the
Crossbar that goes between the Eyebars,
because the two pairs of Eyebars are too close
together to get another Crossbar on top of the Saddle.
So an extension must be used under the second Crossbar to clear the
upper Eyebar.
|
So
What Broke? (early
guesses).
At the very least, a
weld between the Crossbar and the Saddle broke. Here is a
picture taken (we believe) just after the failure.

|
|
Here
we're looking
at two pairs of Eyebars near the top of the
bridge;
the pair closest to the viewer has the crack. There is a Saddle
(the thing with the three rusty-looking plates
side-by-side)
at the top of the central Eyebar. On top of the Saddle (between
the pairs of Eyebars) is an Extension and a big T-shaped Crossbar
that holds the Tie Rods (see
previous picture). But
there is no Crossbar on top of the Saddle nearest the viewer, where
the weld failed, sending it and its Tie Rods
down to the roadbed. Note the crack that started all this fuss in
the central Eyebar
just below the Saddle nearest you.
|
|
|
|
This
photo shows
the Crossbar that is supposed to sit on top
of the
Saddle some 100
feet up in the air at the top of the Eyebar. There are two of
these, one possibly hanging down below the bridge and
this one that went flying around that took out a car. Both Tie
Rods
(that look like cable) are
still attached to this Crossbar in
the photo below
(remember, this was sitting on top of the Saddle in the earlier
pictures) so it doesn't look like a Tie Rod broke at this end. But we haven't
seen the other end.
Caltrans now claims (but not
originally)
that the Tie Rod broke
first. If so, it is inevitable that the unbalanced force
on the end of the Crossbar will pop the Crossbar off of the Saddle, no
matter how good the weld is between Crossbar and Saddle. Clearly
the weld between the Crossbar and the Saddle
failed, but was that the main problem?
|

This is what Caltrans said on the official
website:
"Caltrans District 4 closed both directions of the San
Francisco-Oakland Bay Bridge to repair
the crossbar and two rods
that came loose
[consistent with 'the weld failed'] from
the eyebar repair that afternoon. " [my italics, inserted
comments and bold type]
Other early updates (1,
2,
3,
4,
5,
6),
which gave remarkably few details, indicated
that Caltrans reinstalled the same fix with some
"design enhancements with different elements" added to strengthen the
connections between the
parts. This is also consistent with other statements that blame
"metal
fatigue" (which means metal breaks when it is bent back and forth
enough times). Originally, I thought that Caltrans was refering
to metal fatigue in the weld. In other words, when a
welded joint is
flexed repeatedly, it tends to break rather than bend (see debate below). I originally claimed that
welds
were "remarkably intolerant" to flexure. I later changed this to
"less tolerant" based on a valuable discussion I had with a welding
expert (see reader feedback section). I had guessed that
the
engineers intended to weld on additional pieces of steel over the
joints between the parts. Then these steel pieces would tolerate
some bending and reduce the stress on the welded joint itself.
Or alternatively, extra parts would be welded on to simply minimize the
total amount of flexing, that is, to make the whole saddle/crossbar
assembly more rigid.
But it seems clear that the
failure of the weld was more a result,
not a cause, and we'll see
what the repair is in just a moment.
In retrospect, it is impressive to me that they
managed to cook up the
Repair 1.0 kludge (that what us engineers call an inelegant solution
cooked
up to solve a
problem quickly) in short order, but it was a little
underdesigned
***. It might have been a
better idea to also try to
replace the broken Eyebar soon after the repair was installed.
Were I responsible for this, I would have ordered new Eyebars at the
same time I ordered the parts for this temporary fix and, in the
meantime, begun to think about how to replace them. Replacing
Eyebars will not be trivial, but the upcoming Repair 3.0 scheme turned
out to be an acceptable alternative.
Repair 1.0 lasted two months, yet the crack in the Eyebar
has been hanging up there for long
enough to get nice and rusty (an anonymous source claims two
years); it bends back and
forth as the wind blows, as the traffic load changes from rush hour
peak to the dead of night, and as the
bridge expands and contracts as it heats and cools. So
the original bridge design looks pretty good in retrospect. Don't
you feel better now as you drive across the bridge (maybe one day soon)?
Repair 2.0
-
New Pictures of Repaired Parts and "Design Enhancements With Different
Elements".
As time passed, we found more great pictures of the repair work
that confirmed some of the guesses made above. There were two
principal problems with Repair 1.0:
1. A Tie Rod cracked or broke at the place where it passes
through a Crossbar, and
2. The weld broke between the
Upper Saddle and a Crossbar; an inevitable consequence of the Crossbar
being loaded on only one end by the remaining unbroken Tie Rod.
So let's go fix it!
Lower
Saddle
Assembly: Coupling
Between Crossbars
Here is the
modified Saddle Assembly at the lower end
of the Eyebar. No Tie Rods yet.
(Original photo screen-grabbed
from here)
What is the fix? First of all, in the above photo,
you will see that there
is now a coupling between the two
Crossbars on the lower Saddle
assembly. This, along with better welding between Crossbar and
Saddle, helps prevent the Crossbar from popping off of
the Saddle which was the prior failure at the upper Saddle.
Lower Saddle: Radiused Plates,
Hydraulic Actuators.
We see that some plates have been added to the bottom of the
Crossbars.
The purpose of these parts is to try to deal with the side-to-side
motion of the Tie Rods caused by wind load, traffic load, and
vibration. But how do they
do this? Recent Caltrans reports (
here
is a typical description) say that a Tie Rod broke because
of the stress on the
Tie Rod induced by bending where the Tie Rod connects to the
plate. To reduce the
stress on the Tie Rod, the Nut and the plate against which the Nut
rests have been "radiused", i.e. rounded, so that they "roll" against
each other.
Below is a picture of the Receiving
Plates that shows how the inside edge
of the hole has been rounded out or radiused (see the shiny ring-like
area) to
accept the mating surface of the Radiused Nut.
( Original photo
screen-grabbed
from here)
What is up with all of this? We've
drawn some pictures of the parts to show what can happen.
First, consider the ideal situation. Here's a view
through the top plate of the upper crossbar (although reports are
consistent with a failure at the bottom
assembly, both top and
bottom assemblies were essentially identical). There is a thick
upper plate on the top of the crossbar with a hole drilled through it
for the tie
rod. The tie rod goes straight through the plate and is held in
place with a large nut; there is an identical nut and crossbar on
the other end, some 80 feet below. The tie rod is being pulled
from each end by the loading on the bridge. The load on the tie
rod pulls the nut flush against the surface of the crossbar. The
hole
in the crossbar is a little larger than the diameter of the tie rod and
the tie rod sits roughly in the center of the hole.
However, if the crossbar and tie rod are not absolutely perpendicular
(hard to achieve on such a structure), or if vibration causes the tie
rods to slide around a bit inside the hole (as chairs on a hardwood
floor might slide around during an earthquake), the tie rod can rub up
against the side of the crossbar. Repeated wear at the contacting
surfaces can lead to a failure of the tie rod. Or in the second
picture, because the
pressure on the surface of the nut is now not uniform (greater pressure
at the
corner in contact with the crossbar), the nut itself is also more prone
to failure. Our drawing is exaggerated to more clearly show the
effects.

|
|

|
So one approach is to radius the nut and the plate onto which the nut
rests. Then, the tie rod is free to take on a tilted
orientation while still providing uniform contact between nut and plate
surface, and the tie rod can be kept centered on the hole and away from
the sides of the hole in
the plate. The existing nuts can be radiused, or one can purchase
nuts from Williams Form Engineering that look like the nuts in the
picture below-left that have a broader foot with greater surface
area. This larger foot was not used on the Bay Bridge nuts
because the severe tilt which we display in our graphic was not
expected, so the radiused surface was simply milled onto the surface of
the existing nuts. In
the bridge repair, an extra plate with a spherical "cutout" has been
added
to the
top of the existing crossbar because it would be impractical to try to
machine these spherical surfaces onto the unwieldy
crossbars/saddles. A larger hole (extra clearance) is also
drilled into the mating plate that has been radiused.

|
|

|
So it is not as if the radiused nut and plate are continually
rolling
against each
other, but there can be some vibration or changes in traffic loading
that would otherwise cause the nut and rod to drift. The radiused
surfaces prevent this. We expect these new parts
will be periodically checked and
retrofitted if
necessary, during the three Fridays per month that the bridge is to be
closed (note on Nov. 5: now daily
inspections).
The lower Crossbar
has
been fitted with pedestals, i.e. each
radiused Receiving Plate
sits up on a pedestal or raised platform. There are some other
photos floating
around
the web that indicate that an earlier idea was to install some sort of
pneumatic cylinders on the ends of the lower Tie Rods that required
this pedestal. We thought that this scheme has been abandoned,
because there were pictures without the cylinders installed. This
pedestal
affair is weaker than simply welding together two fat, flat
plates
(as
they did on the upper
Crossbar), and it also puts more "leverage" on the weld
between
the
Crossbar and Saddle. So we can conclude that this project
is
really evolving and changing even as I write this.

|
|
On the morning of Nov.
2, we found out what Caltrans was doing
with the
pedestals:
"During stress test late
Sunday,
workers used a mechanism to pull at
the
entire assembly, which allows them to measure the amount of strain it
can withstand."
They add hydraulic actuators (the cylindrical things that look like
coffee cans with the tubing coming out of the sides) to the end of the
Tie Rods. These are like the pistons used on heavy
construction equipment, such as on a bulldozer to move the blade
around. Here, they are used to give the
Tie Rods a pull and then allow engineers to watch what happens.
Engineers can then calibrate
their
strain gauges and watch the Tie Rods stretch. My guess is that
they would like to see the crack in the Eyebar close up a bit so that
they know some
load has been removed from the cracked Eyebar, but they also want to
know that the amount of tension required to do this is less than the
known strain limits of the Tie Rods and Nuts.
As seen on our drive across the bridge, these
hydraulic
actuators became part of the permanent installation of Repair
2.0. So now
we have radiused Receiver Plates and
Hydraulic Actuators at the lower Saddle assembly.
|
Upper Saddle : Radiused
Plates, No
Cross Coupling
Now, what was modified at the upper end? Below is a
picture
of
the Saddles and Crossbar at the
Upper part of the Eyebar,
prior to any
modifications. The Eyebar with the crack is on the opposite side
(not visible) and is
the lower of these two sets of bars. Two Crossbars are in
place; the upper Crossbar has an extension
between it and the Saddle so that everything fits correctly. No
Tie Rods are installed.
Here is what the same end
looks like
after
modification.

We see that radiused Receiver Plates have been added to the tops
of the
Crossbars without the Pedestal used for the hydraulic actuators on the
lower Saddle.
But more important, there is no
visible coupling between
the
two
Crossbars on the upper
assembly because the Crossbars are not lined up
side-by-side as in the lower
Saddle assembly, making such a modification tricky!! So
hiding between the Eyebars is (hopefully) a
coupling that we cannot see that helps prevent the upper Crossbar from
popping off like it did just a few days ago! This is a major
component that we will look for in future photos! The Caltrans review says
that the original tack
weld used between the Saddle and Crossbar (two pieces welded together
at small points in several locations) which broke, has been
replaced with a more thorough weld - "Enhanced Welding" - between the
two surfaces. So this is consistent with not seeing a coupling
between the upper Crossbars! Caltrans thinks they need
cross-couplings at the lower
assembly but not the upper
assembly?
Upper Saddle : Better
Weld

(Original photo
screen-grabbed
from here)
|
|
Here is a photo of the improved
welding (before
the receiver plates are added on top). While it is clear that the
weld is more substantial than before, there are some obvious problems
to consider. The first is that the contact area between the
Crossbar and Saddle occurs in only the spots where the sets of bars
(two for the Crossbar and three for the Saddle) overlap. So the
welds are only as large as the overlap, perhaps 3" square, since the
plates in the Saddles and Crossbars appear to be about 3" thick.
It's
hard to get a welding torch between the plates so most likely only the
edges of the bars are welded. I hope this does not leave an open
seam at the back of the joint that will allow salt water to creep in
between the joint. But it is still a better joint than Repair
1.0, and remember, the Crossbar and Saddle are being pulled together by
the Tie Rods anyway.
The second is to ask why Repair 1.0 broke in
the first place. The two long arrows show how the Tie Rods will
pull equally on each end of the Crossbar when they are installed, like
the weight of two children on either side of a seesaw. If one Tie
Rod breaks (the previous failure), then there is a very large force (a
rough calculation gives a number of over 100 tons) that is unbalanced
on the end of the Crossbar that tends to pop the weld off. The
hydraulic actuators may be used to insure that there is uniform tension
on the Tie Rods, thereby balancing the force on each end of the
Crossbar, and minimizing stress on the improved weld. But all
bets are off if a Tie Rod breaks.
|
Finally, there
are some other devices (which we have not seen in photos) used to
reduce the vibration of the Tie Rods
themselves, along with monitoring strain gauges (these measure Tie Rod
stretching) which tells me
that
the engineering crew wants to know just how much load they
have on the Tie Rods. The vibration dampers are attached to these
bolts
(below) between pairs of adjacent Tie Rods. We don't have
pictures of the strain gauges, also attached to the Tie Rods. As
the Tie Rod stretches,
it pulls on the Strain Gauge, and directly measures the actual
lengthening of the Tie Rod (it's like attaching a measuring tape to the
Tie Rod).
This picture (below) displays how the vibration dampers are
affixed.
How does this assembly work? The tie
rods
are on the outside; the eyebars are in the middle. They have
taken large slabs of what appears to be high-density foam or a material
called Sorbothane, which is a dense, rubber-like material used for a
variety of vibration-damping applications. They bolt big slabs of
this to the eyebars with a simple clamp. Then the slabs that are
furthest out simply press against the sides of the tie rods.
Further, all four tie rods are attached together in sets by using
long turnbuckles. Here is another view:
See how the Sorbothane slabs simply press against the side of the tie
rods. This allows the tie rods to move, but oscillatory motion
(like a guitar string)
that would develop because of wind or road vibration is dampened or
absorbed by the Sorbothane pads. Also note that foam rubber tubes
of the
kind that can be purchased in your local hardware store for insulating
the water pipes that go to your hot water heater, have been added over
the tie rods (slice the side, slip it over the tie rod, add lots of
tape) to prevent them from banging against the eyebar joint.
All of this tells me that the Bay Bridge
moves
a lot! A reader
has pointed out
this
article which indicates that vibration of the Tie Rods has been a
concern at Caltrans after Repair 1.0 was installed and before the
failure:
"We didn't get the modifications put
in place in this for the latest
windstorm," Fey said. Gusts of more than 50 mph Tuesday were a
'contributing factor,' increasing vibrations in the metal rods, he
said."
I've lived in the Bay Area for 20 years. It
blows like this
every year, several times a year. It is becoming more and more
clear that the implementation of the Tie Rods is a substantial
challenge and a work-in-progress.
Installing Tie Rods
Below we see the upper
Saddle assembly with Tie Rods being installed. Hiding under those
nuts (right above the yellow jacket of the center ironworker) on the
Tie Rods are the radiused
surfaces that allow the Tie Rods to tip side-to-side a little more
freely and not bind against the inside of the plates.
Here we are getting a little more serious about tightening the
Nuts. One ironworker has his hands on the wrench, and another is
applying some extra force.
But why? It is simply not necessary to crank on the nuts like
this, because the
hydraulic actuators on the lower
crossbar/saddle are going to do the real work of tensioning the Tie
Rods. So in spite of the dates on the photographs, this may be
Repair 1.0.
Again, we see no connection between the Crossbars (Dude, the brim
of the hat goes over your
forehead and the chin strap goes under
your chin! Is this an OSHA violation?? Maybe not: my
anonymous source says the
welders always wear their hats backwards. How do we know he's a
welder? Because he has those protective welding pants on).
Conclusions,
Post Repair 2.0
So the conclusion so far is that the repair is essentially the same
scheme as fabricated on Labor Day weekend, with some important
improvements, hopefully some of which are hidden from view.
1. Engineers are putting a lot of effort into understanding the
forces
on the Tie Rods. They are, and have been, worried about how much
they vibrate,
about what they rub up against as the bridge moves and as the rods
vibrate, and about the
stress on the Tie Rods as they pass through the Receiving Plates.
They are constantly monitoring the forces on these Tie Rods and are
using hydraulic actuators to provide a known tension, or pull, on
the Tie Rods (presumably uniform between
all
rods)
. If a
Tie Rod fails, there's a good chance that some of
the components of the Saddle/Crossbar assembly will once again come
loose. Also, see our calculation of the
stress in the Eyebar and Tie Rod
here.
2. They have improved the weld between the Crossbar and Saddle
and even added some extra pieces to hold the Crossbars on at the lower
Saddle, but they've
done different things on the upper and lower Crossbars, adding
hydraulic actuators to tension the Tie Rods.
They have essentially replaced an Eyebar (that lasted 70 years) with an
arrangement
of rods and brackets (whose first version lasted 2 months). And
the cracked Eyebar is still there.
Caltrans (November, 2009) closes the #1 lane of the
bridge every day for
an hour and a half just after lunch to monitor the strain gauges and
observe the parts. My guess is that they need to do it in mid-day
because they want to monitor the repair under traffic conditions.
I
think it's a good idea that the
same
engineers monitor the repair
each
day (not just a crew that goes
out and takes notes) so that any trends that might point to
deterioration become obvious. So monitoring needs to be done
during the
day so that the engineers also get a good night's sleep.
Some Monitoring and Testing
Ultrasound
For example, here is some ultrasound testing
going on (albeit at night in mid-November) on one of the pins that
connects a set of
eyebars together.

|
|
The
operator in front is holding a Panametrics-NDT Epoch LT ultrasound
flaw and thickness detector (you can do a Google search to find out
about this device). It sends out a pulse of sound at extremely
high frequency (inaudible) from a transducer being held against the pin
by the operator in the rear (think earphone connected to an
iPod). The sound propagates through the material, in this case,
the big steel pin that you see running horizontally between the eyebars
(not that silly little bolt sticking out),
and bounces off of the far end of the pin (to the left) and is
reflected back to the transducer. The sound is also reflected off
of any cracks or perturbations (like a change in pin diameter at a
flange). This is similar to ultrasonic imaging used for medical
applications.
|
Here is the screen display showing the reflected
sound intensity.

|
|
What
you see on the screen is a plot of
the reflected sound amplitude versus the depth within the
material. The big
burst of hash on the left side is sound being reflected from the poor
mechanical interface between the transducer and the pin itself, and the
spikes on the right side show reflections from the opposite end of the
pin. The cursor is set on the second
big spike and the number at
the top of the display, 45.800 inches, corresponds to that spike,
indicating a place in the pin that reflects a lot of sound, and appears
to be the
total length of the pin. The first
big spike, easily calculated
to be at 42.6 inches, could be from a big crack or it could be from a
flange or a counterbore machined into the end of
the pin, like this one:
|
"Whew," he says, as he compares the counterbore depth on the
tape
measure with the number
on the ultrasound tester, "no crack!" "Let's put the cap back
on [held on with a big nut] and go have a beer!" What does "UTOK
10/09" mean? I guess "ultrasound test OK, Sept.
9". So since this is Nov, '09, is this a second test?

(Photo source)
Stress
Monitoring
Late in December, after Repair 3.0 had begun,
we grabbed this screenshot from a Caltrans video, clearly shot from the
inside of a van. We see a big screen displaying the output from a
bunch of strain gauges placed who knows where on the bridge. Each
readout is in thousands of pounds. It looks like this particular
application has been written in LabView, an application particularly
useful for reading sensors and performing real-time control of
actuators. The positive numbers are probably measurements of
tension as would be found in
elements like the eyebars or tie rods and the negative numbers are
probably measurements of
compression
as would be found in the lattice girders or roadbed elements. The
graphical plots in the middle allow the monitoring of trends, which can
provide a clue of something beginning to fail; straight
lines are a good sign. The "1954" number (representing 1,954,000
pounds) is pretty darn substantial (977 tons) and most likely
represent the tension in some of the massive upper eyebars at the top
of the bridge (see our
analysis).
In principle, one could actually automate the system and provide active
feedback on the hydraulic actuators used on Repair 2.0, but I'm
betting they don't. I'm guessing that a Windows crash (the Blue
Screen of Death) in such a case might not be a good thing.
Repair 3.0
Click here for all the cool
and groovy stuff for Repair 3.0 on page 2! (loading a
separate
page helps your
browser move more quickly)
Don't go back to the rest of your life, you really want to know all about this bridge
thing!!
____________________________________________________________________________________________________________________________________
Interesting
Viewer Feedback - Repair 1.0 and 2.0
I am surprised at
the interest this page has generated. Many readers have sent me a
variety of comments, questions and links to other information.
Most recent comments get added to the top of the list.
My Snail Mail Comment.
a) Don't do a
search on my snail-mail address and send me
things without sending me a note by e-mail
first! It's way creepy! Please use my e-mail address above
to send a comment or
question.
b) Don't send me
snail-mail unannounced; how do I know that you're not some kinda
nut that would send me anthrax in your letter? I'm not even going
to open your mail; it goes straight to the trash!
c) Don't send me
reams
of
paper because I'm not going to read them; while it might appear
otherwise, I have a life, too. If you feel compelled to send a
lot of stuff, please post it on-line somewhere, and send me a link to
it.
d) Stay on-topic and stick to the
subject, which is "what was the repair", "why did it break", "is the
new repair going to work", "is there a better way" and "where can one
get a really good martini in San Francisco (besides Zuni Cafe) or Santa
Fe (besides Coyote Cafe)".
I can't comment on the
new
Bay Bridge design; I haven't studied it yet, therefore I can't
speak intelligently about it. Please ask this
guy; he will have a lot to
tell you.
Radiused Nuts. A member
of the Stanford University community has pointed out that the KRON
article
says that the purpose of the radiused nuts/plates is to center the tie
rods in the receiver plates while I've alternatively emphasized the
Caltrans
claim that
the nuts and
plates are
radiused to allow rotation (more accurately, "pivoting"). I
claimed that that latter would not work very well; the reader thinks I
should emphasize the former. I now think that Caltrans means
exactly what they say; they did it for
both reasons. But I began
thinking
why? Did the
Tie Rod snap because it flexed against the Crossbar? Or did it
snap at the Nut itself? The weakest point anywhere on a
threaded bolt is at the thread and where the nut and thread
"connect". Are the Tie Rods too small in diameter to
tolerate the stress
at the Nut.
Is the solution simply to use larger diameter Tie Rods? Will
larger diameter Tie Rods not fit because there is not enough
space between the two parallel plates that form the Crossbars?
Hydraulic Actuators. A
reader
(P. T.) has mentioned that the hydraulic actuators might be used to
compensate for the different thermal expansion of Tie Rods and
Eyebars. This is possible if the Tie Rods and Eyebars are made of
different types of steel. And since an unbalance in the tension
of Tie
Rods was partly responsible for the failure of the weld between Tie Rod
and Crossbar, keeping the Tie Rod tension uniform is also
important.
This can be monitored with the strain gauges that have been installed,
and controlled with the hydraulic actuators.
Corrosion Prevention. Have any
of you seen any painting on the Bay Bridge lately? One of the reasons
that the bridge gets painted is to help stop corrosion that might lead
to cracks. Sometimes you need to do more exotic things (like on pins
and eyebars) because you have to get in between the small spaces (like
on the cracked eyebar). One experienced viewer (William L.)
familiar with Bay Bridge
Paint Crew says that this sort of maintennance is no longer performed
on the Bay Bridge, assuming that the eastern span would be removed in
2013, hence no longer needing the paint. Would paint and corrosion work
have prevented the eyebar crack? I certainly do not have the background
to tell you.
Stability of the Repair.
I've been having an interesting discussion with an engineer (E. F.) who
has
also discussed this issue with some UC Berkeley faculty and also with
another reader (Mark M). The issue is one of the inherent
stability of the
repair. This is comparable to the idea of balancing a pencil on
it's point: it may actually be possible to do that (for a very
short time) but any perturbation sends the pencil to the table.
It has been proposed that the repair (saddles, crossbars, tie rods) has
this same inherent problem, one of
stability,
and depends critically on the friction between the big fat pins (that
connect the ends of the eyebars) and the saddles that sit on these
pins. I've been doing these calculations myself and don't see
that problem, but I'll work on it a bit more and see what I find.
I've
not heard back from him, so after reviewing his calculation, he may
have come to the same conclusion as I.
Rigging Techniques. A
welding
rigger (T. R.) commented on how one could weld on various pieces (dogs
and
shaped saddles) onto the unbroken eyebars above and below the failed
one. These pieces would be used to hold a "stopper" in place
(essentially a loop of cable around the undamaged eyebars).
Block-and-tackle are added (cables and a way to tighten them), the load
on the cracked eyebar is removed and the eyebar replaced.
About Replacing Eyebars.
This comment from Patti B. get a Pulitzer Prize:
"I've been wondering why they don't
just bite the bullet and replace the eyebar as well. I can
certainly see how doing so would be a significant engineering effort,
but no more so than slicing out a chunk of the bridge and swapping in a
new one."
Comparison with the Silver
Bridge. Several readers have pointed me to webpages that
describes the
Silver Bridge collapse in Ohio, a bridge of about the same vintage as
the
Bay Bridge, in which the collapse was caused by the failure of an
Eyebar.
http://labspace.open.ac.uk/course/view.php?id=3350&topic=all
and
http://en.wikipedia.org/wiki/Silver_Bridge_%28bridge%29
Now I must point out that the type of bridge described in the above
document is of a type more like the
west
span of the Bay Bridge (a
suspension bridge) and not like the
east
span of the Bay Bridge (a
double cantilever). It does appear that there are many parallel
Eyebars in the Bay Bridge at the location of the cracked Eyebar that
share the same load. So if one breaks, there are others that act
as a backup. But it is interesting to see that Eyebars are a
common component in many different bridge styles and that they have
been known to crack before, and in fact, the very top section of the
Bay Bridge is full of Eyebars.
Corrosion-induced Cracks.
One reader points out that on the Silver Bridge
"the corrosion crack likely was the result of water collecting
in the
eyebar hole in a spot where it was inaccessable to painting, as
well as the
fact that there's a greatly increased (2-3)x concentration of
stress around
the eyebar hole."
One could imagine the same problem, exacerbated by salt water, on the Bay Bridge.
Other Bridge Failures. And while the Bay Bridge has not actually "failed" yet, here is a large
list of failures offered by a reader: http://en.wikipedia.org/wiki/List_of_bridge_failures
____________________________________________________________________________________________________________________________________
A
Debate! I've had a lively discussion with a
welding instructor at a community
college in New
Hampshire who claims that a
properly-welded joint can have tensile strength (the measure of
strength that matters in bridge structures) equal to the basic material
used on either side of the weld if the welded region is made oversized
and properly designed. We know that the original Caltrans welds
were
only
tack welds (not the full
surface between the
two metal elements) so these sorts of welds are unquestionably not as
strong as if the weld were "full". It may imply that if
the weld is "enhanced" to use Caltrans words, that the weld can be
successful. However, as I read "Fatigue Strength of
Welded Structures" by Stephen John Maddox, and other references
on-line,
I see that, in general, a welded
joint is less tolerate to fatigue (repeated bending) than the starting
material. So while the original weld may be strong, it weakens
faster than the rest of the material as it is bent back and
forth. The instructor has pointed out that virtually all large
structures have welded joints and survive well for extended
periods. While I agree, my counter is that engineers compensate
for the greater rate of fatigue failure of welded joints by designing
the structure to place bending forces at places within the structure
that better tolerate these forces. For example, bridges are
designed so that forces that bend the structure are placed at places
where the joints are pivoted. For the meantime, I've rephrased
my statement
to
say that welded joints are "less tolerant" of repeated bending, and
meanwhile I'll try to find a definitive reference in the
literature. Also, the instructor has assured me that portable
equipment exists (as opposed to some large, fixed welder within a
factory environment) that is sufficient to do the best possible weld
100 feet up in the air at the end of a 'cherry picker'.
**A
Correction
Originally I thought that the repair had used a combination of
Tie Rods connected to Cables, or what is known in the rigging industry
as Wire Rope. There are Federal
Standards
for the manufacture of this stuff and it is incredibly strong and
tolerates flexure (bending). Fittings can be crimped (squeezed)
onto the
ends of the
cable and the crimp, if made properly, is actually as strong as
the wire rope itself. I supposed that the Tie Rod was
hollow at one end and the cable was fitted inside and welded or crimped
on, like
this
device. It now appears that the Tie Rods are indeed one
long
continuous rod, with threads on the outside. I don't see any seam
in these Tie Rods (below)
that would show a
separate rod and cable connection.
Months after this article was first started, we discovered that the Tie
Rods are made by Williams Form Engineering Corp. and are available
here.
This is strong stuff but it does not like being bent. One day, we
may discover if and/or why one of these failed.
Footnotes
* Some lattice girders are under compression,
some are under
tension, but all of these needed to tolerate some compression when the
bridge was being built.
*** See our new stress analysis of the eyebar here.
A reader on another (one of many) blog on this subject objected to my
accusation that the solution was "underdesigned". Well, it broke,
no? However, I must admit that, based on my static modeling
(a model that does not account for vibration), I'm not exactly sure why
it broke.